Safety risk assessment of prefabricated building construction based on IM-FCM
Email: zhuke2018@whut.edu.cn;
DOI: 10.13637/j.issn.1009-6094.2022.0100
Published:   2022-07-08
Publication Date:   2022-07-08
Online:   2022-07-08
Mobile reading
Abstract:

Aiming at the problem of insufficient dynamic interpretation capability of existing safety risk assessment methods, this research aims to accurately evaluate the safety risk of prefabricated building construction and improve the level of construction safety management. To achieve this purpose, a Level 2 Risk Assessment architecture of work breakdown structure and risk breakdown structure is used to establish a safety risk assessment index system for prefabricated building construction. A Combination Ordered Weighted Averaging(C-OWA) operator to quantify the subjective scores of experts is introduced to construct a coupling interaction matrix. Using the fusion model of the interaction matrix and a fuzzy cognitive map, identification of key risks and prediction of safety evolutional trends can be obtained, which is verified by an empirical analysis of safety risk levels in a project in Wuhan City, China. The assessment results indicate that: this project shows high risk overall, which is almost in line with the actual situation of the project. With the interactive coupling and evolution of construction safety risk, the risk assessment coefficient is found to be increased by 10.28%, and the risk rises from Level Ⅲ to Ⅱ, indicating the probability of safety accidents increases. This result requires implementing dynamic risk early warning in the whole construction process. The risk-related risk factors with a high degree of importance warrant are primarily controlled, including “defects occur to vertical or horizontal component supporting systems”, “quality control and safety risks caused by improper treatment existing in construction sites”, “collision between hoist components which are not operated according to construction plan”, “improper protection in marginal operation, high latitude operation and climbing operation” and “operation errors caused by defects existing in cranes and hoisting equipment”. The fusion of the interaction matrix and a fuzzy cognitive map can obtain both the dynamic assessment of construction safety risks and the prediction of construction safety risk evolution from the temporal dimension. This quantitative method can largely reduce the subjectivity of risk assessment and improve the dynamic interpretation of the assessment model.

References

[1] 中华人民共和国住房和城乡建设部.关于印发“十四五”建筑节能与绿色建筑发展规划的通知[EB/OL].[2022-09-18].http://www.gov.cn/zhengce/zhengceku/2022-03/12/content_5678698.htm.Ministry of Housing and Urban Rural Development of the People’s Republic of China.Notice on printing and distributing the development plan of building energy conservation and green building in the 14th Five-Year Plan (2021-2025)[EB/OL].[2022-09-18].http://www.gov.cn/zhengce/zhengceku/2022-03/12/content_5678698.htm.

[2] LUO T,XUE X L,WANG Y,et al.A systematic overview of prefabricated construction policies in China[J].Journal of Cleaner Production,2021,280(1):124371.

[3] MA W D,SUN D C,DENG Y S,et al.Analysis of carbon emissions of prefabricated buildings from the views of energy conservation and emission reduction[J].Nature Environment and Pollution Technology,2021,20(1):39-44.

[4] LIU J K,GONG E Q,WANG D,et al.Cloud model-based safety performance evaluation of prefabricated building project in China[J].Wireless Personal Communications,2018,102(4):3021-3039.

[5] FARD M M,TEROUHID S A,KIBERT C J.Construction of manufactured homes:understanding the hazards and risks[J].Professional Safety,2017,62(4):34-40.

[6] LU Y,ZHU Y Q.Integrating hoisting efficiency into construction site layout plan model for prefabricated construction[J].Journal of Construction Engineering and Management,2021,147(10):4021130.

[7] LIU Z S,MENG X T,XING Z Z,et al.Digital twin-based safety risk coupling of prefabricated building hoisting[J].Sensors (Basel,Switzerland),2021,21(11):3583.

[8] CHANG C G,WU X,YAN X.Multiobjective optimization of safety risk of prefabricated building construction considering risk correlation[J].Mathematical Problems in Engineering,2020,2020(1):3923486.

[9] 王乾坤,朱科,王军武,等.工程项目风险管理文献计量分析[J].中国安全科学学报,2021,31(7):15-23.WANG Q K,ZHU K,WANG J W,et al.Bibliometric analysis of engineering project risk management literature[J].China Safety Science Journal,2021,31(7):15-23.

[10] ZHANG G D,XUE Y G,BAI C H,et al.Risk assessment of floor water inrush in coal mines based on MFIM-TOPSIS variable weight model[J].Journal of Central South University,2021,28(8):2360-2374.

[11] 王乾坤,亢显卫,朱科.地铁深基坑施工风险耦合评价方法[J].东北大学学报(自然科学版),2021,42(8):1152-1158.WANG Q K,KANG X W,ZHU K.Coupling evaluation method of the construction risk for subway deep foundation pit[J].Journal of Northeastern University (Natural Science),2021,42(8):1152-1158.

[12] 潘梦真,虢成功.基于改进相互作用矩阵的基坑施工安全风险评价[J].中国安全生产科学技术,2020,16(3):125-130.PAN M Z,GUO C G.Safety evaluation of foundation pit construction based on improved interaction matrix[J].Journal of Safety Science and Technology,2020,16(3):125-130.

[13] KHANZADI M,NASIRZADEH F,DASHTI M S.Fuzzy cognitive map approach to analyze causes of change orders in construction projects[J].Journal of Construction Engineering and Management,2018,144(2):4017111.

[14] SONER O,ASAN U,CELIK M.Use of HFACS-FCM in fire prevention modelling on board ships[J].Safety Science,2015,77:25-41.

[15] WANG L,LIU Q,DONG S Y,et al.Effectiveness assessment of ship navigation safety countermeasures using fuzzy cognitive maps[J].Safety Science,2019,117:352-364.

[16] 杨佳宇,段文杰,李廷文,等.基于模糊认知图的水上交通事故涌现分析[J].交通信息与安全,2019,37(4):19-26.YANG J Y,DUAN W J,LI T W,et al.An analysis of emergence of water traffic accidents based on fuzzy cognitive map[J].Journal of Transport Information and Safety,2019,37(4):19-26.

[17] 周娟,余忠华,侯智.模糊认知图与证据理论融合的质量控制决策模型[J].系统工程理论与实践,2016,36(5):1288-1296.ZHOU J,YU Z H,HOU Z.Fuzzy cognitive maps and evidence theory based research on quality control decision-making model[J].Systems Engineering—Theory & Practice,2016,36(5):1288-1296.

[18] ZHANG L M,CHETTPUZHA A J A,CHEN H Y,et al.Fuzzy cognitive maps enabled root cause analysis in complex projects[J].Applied Soft Computing,2017,57(1):235-249.

[19] LI X H,ZHANG L Y,ZHANG R R,et al.A semi quantitative methodology for risk assessment of university chemical laboratory[J].Journal of Loss Prevention in the Process Industries,2021,72:1-11.

[20] 吴红刚,马惠民,张红利.基于相互作用矩阵的山区公路展线路基稳定性评价[J].岩石工程学报,2011,33(增1):202-206.WU H G,MA H M,ZHANG H L.Evaluation of subgrade stability of mountainous highway exhibition based on interaction matrix[J].Chinese Journal of Geotechnical Engineering,2011,33(S1):202-206.

[21] 贺政纲,郭静妮,徐君翔.基于WBS-RBS和PFWA算子的多式联运网络安全风险评估[J].安全与环境学报,2020,20(2):441-446.HE Z G,GUO J N,XU J X.On the safety risk assessment of the multimodal transportation network based on the WBS-RBS and PFWA operator[J].Journal of Safety and Environment,2020,20(2):441-446.

[22] 湖北省应急管理厅.省应急管理厅关于印发《湖北省安全生产风险管控办法(试行)》的通知[EB/OL].[2021-04-05].http://sft.hubei.gov.cn/bsfw/bmcxfw/gfxwjcxxt/202102/t20210226_3364823.shtml.Hubei Provincial Emergency Management Department.Notice of the Emergency Management Department of Hubei Province on printing and distributing the Measures for the Control of Work Safety Risks in Hubei Province (for Trial Implementation)[EB/OL].[2021-04-05].http://sft.hubei.gov.cn/bsfw/bmcxfw/gfxwjcxxt/202102/t20210226_3364823.shtml.

Basic Information:

DOI:10.13637/j.issn.1009-6094.2022.0100

China Classification Code:TU714

Citation Information:

[1]WANG Qiankun,ZHU Ke,GUO Peiwen ,et al.Safety risk assessment of prefabricated building construction based on IM-FCM[J].Journal of Safety and Environment,2023,23(07):2202-2211.DOI:10.13637/j.issn.1009-6094.2022.0100.

Fund Information:

海南省重大科技计划项目(ZDKJ2021024);; 三亚崖州湾科技城海南专项博士研究生科学研究基金项目(HSPHDSRF-2022-03-001)

Published:  

2022-07-08

Publication Date:  

2022-07-08

Online:  

2022-07-08

Search Advanced Search